Bearspaw South Feeder Main Improvements Project
Community information sessions
Join us to learn more about essential feeder main construction in your community.
Online information sessions
February 24
6 p.m. – 7:30 p.m.
Microsoft Teams
February 26
12 p.m. – 1:30 p.m.
Microsoft Teams
In-person information sessions, drop-in format, arrive any time
March 5
5 p.m. - 8 p.m.
Bowness Ratepayers Scout & Guide Hall
8551 Bowness Rd NW, Calgary, AB T3B 0H8
March 7
10 a.m. - 1 p.m.
Terrace Road School
2103 46 St NW, Calgary, AB T3B 1B3
Overview
The City is implementing a revised plan that urgently expedites construction of a replacement for the Bearspaw South Feeder Main (BSFM) due to the critical condition of the current pipe and its importance in Calgary’s drinking water system.
The project will add a parallel steel pipe of the same size as the existing BSFM. Over time, this new pipe will take over service from the current line. The replacement pipe is now anticipated to be completed in December 2026.
This work is an important investment in water infrastructure to support system reliability and reduce the risk of feeder main issues or failures.
Project update
Correction: A corrected map has been posted with the construction notice below.
- Bearspaw South Feeder Main: January 2026 construction notice
- Bearspaw South Feeder Main: January 2026 geotechnical notice
Project stages
The project will happen in two stages:
- Stage A: From the Shaganappi Pump Station to 73 Street NW on the west side of the Bow River.
- Stage B: Continues from 73 Street NW to 89 Street NW, with a potential extension to the Bearspaw Water Treatment Plant.
Stage A construction
The City will be proceeding with microtunnelling on Stage A for the feeder main replacement. With The City exploring all options to deliver this project faster than originally planned, we mobilized to sites on January 23, 2026.
Microtunnelling is planned for Stage A due to the existing pipe alignment having significant crossings such as 16 Avenue, the Bow River, Sarcee Trail and the CPKC rail line. While some surface work will be required, work can happen at targeted locations instead of along the entire corridor. Microtunnelling is the best practical option for this stretch as the buried infrastructure we need to reach can be best accessed in this targeted manner instead of needing open trenches along the corridor.
Stage B Construction
Construction of Stage B of the new steel BSFM pipe is expected to begin in May 2026 and will take approximately five months, estimated to be completed by October 2026.
Stage B will span 34 Avenue NW, from 73 Street NW to 89 Street NW, and will be constructed using an open-cut method. This approach allows the work to be completed more efficiently and significantly reduces the overall construction schedule.
Stage B open-cut construction involves:
- Crews excavating a trench along the road right-of-way
- Installing the new pipe directly in the open trench
- Backfilling the trench and restoring the surface once work is complete
Open-cut construction will be sequenced in large sections along the alignment, with one or two sections completed at a time. As each section is finished, the roadway will be reopened, and crews will move to the next area. This approach helps reduce the duration of localized impacts. More details on construction sequencing and section locations will be shared as it becomes available.
Open-cut construction impacts for residents in the area include traffic disruptions, noise, street parking impacts, dust and changes to local access.
Outreach and information
We recognize the impact of the 2024 and 2025 feeder main breaks to businesses and communities and the importance of timely, considerate communications to interested parties so you know what's happening.
Over the coming weeks and months, we are committed to working closely with the community to provide greater detail of construction activities, address unique needs of individual residents and support mitigation efforts where practical. Information sessions will take place virtually and in person starting the end of February and more information will be shared about events as it comes available.
We are sharing information as soon as it becomes available and we are committed to keeping you informed.
Frequently asked questions
How is construction being planned?
Construction is planned to happen in two stages, Stage A and Stage B. Stage A began with site setup and crews mobilizing on January 23, 2026.
Construction of Stage B of the new steel BSFM pipe is expected to begin in May 2026 and will take approximately five months, estimated to be completed by October 2026.
Stage B will span 34 Avenue NW, from 73 Street NW to 89 Street NW, and will be constructed using an open-cut method. This approach allows the work to be completed more efficiently and significantly reduces the overall construction schedule.
Where will work happen?
Stage A alignment is from the Shaganappi Pump Station located near Edworthy Park and extends to 73 Street NW. Stage B will further extend the line, making a connection from 73 Street Crescent NW to 89 Street NW.
Will the Bearspaw South Feeder Main remain operational throughout the improvements?
Yes, it is expected that the feeder main will continue to remain in service, except for short durations when the new pipe needs to be tied into the existing feeder main.
When does construction start?
Construction on Stage A began with site setup and crew mobilizing on January 23, 2026. Stage B, 73 Street NW to 89 Street NW, is expected to begin in May 2026 and will take approximately five months, estimated to be completed by the end of October 2026.
Where can I ask questions about the project?
We are planning information sessions for interested parties in early 2026. More information on those sessions will be available soon. In the meantime, if you have questions or concerns, please don't hesitate to contact the project team directly at BSFMProject@calgary.ca.
What is microtunnelling?
A tunnel construction technique used to construct pipe underground. It includes a microtunnel boring machine that creates the tunnel and then pipes are inserted behind the machine. This construction technique has been used by the water utility for other large diameter pipes, including the Inglewood Sanitary Trunk crossing of the Bow River and Nose Creek Sanitary trunk adjacent to Deerfoot Trail. Microtunnelling is the method of construction selected for Stage A of the project due to the existing pipe alignment and significant crossings.
Can you provide details on other feeder main projects?
The North Calgary Water Servicing Project The North Calgary Water Servicing Project (NCWS) will construct a new 22 kilometre water feeder main and multiple support facilities. The project is essential in providing adequate water supply for future population growth in the northwest area of the city while adding redundancy to our overall water distribution system. Construction of the feeder main is expected to be complete by the end of 2028, with facility construction and system commissioning finalized by the end of 2029, at which point the entire system will be in service.
The South Calgary Water Servicing Project is in early development and will provide the remaining system redundancy to the Bearspaw South feeder main and two other feeder mains. This project is a new feeder main to move water to south Calgary from the Bearspaw Water Treatment Plant that is planned to be complete by 2031.
Crosstie Feeder Main Project will improve the redundancy of the feeder main network in NE Calgary and improve system pressures in Saddle Ridge, Taradale, Martindale and Falconridge. This feeder main extends along Country Hills Blvd from Coventry Hills Blvd to 60th Street NE and will be constructed by 2029.
Contact
If you have questions or feedback about the project, we’d like to hear from you.
- Email: BSFMProject@calgary.ca
- Submit a 311 Service Request online
- Call 311