Sign up for our email updates to receive the most up-to-date information about the Altadore-North Glenmore construction projects.
Have questions or concerns? Email our project team at: AltadoreGlenmoreArea@calgary.ca
Altadore-North Glenmore Construction Projects - Information Session
Date: Wednesday, March 26, 2025
Time: 6:30 p.m. - 8:30 p.m.
Location: North Glenmore Park Community Association
Come learn about the planned work in the area and meet the project teams who will be delivering the improvements and new infrastructure at our collaborative information session.
The City of Calgary is investing in public spaces, recreation and roadway infrastructure in the Altadore-North Glenmore area, with construction of several significant projects kicking off in 2025.
These projects will deliver new twin-arena and track and field facilities at Glenmore Athletic Park, upgrade the 50 Avenue S.W. roadway from Crowchild Trail S.W. all the way into Sandy Beach Park (including parking lots), new multiuse pathways, resurface Glenmore Trail S.W. from Crowchild Trail S.W. to Elbow Drive S.W. and replace the noise barrier along Crowchild Trail from Glenmore Trail S.W. to 50 Ave S.W.
City teams are working collaboratively to coordinate projects to help mitigate impacts and provide community members with up-to-date information on timelines, detours and milestones.
Projects displayed on the map are subject to change in scope.
Details and schedules subject to change
Location | Construction Details | Anticipated Schedule | More information |
---|---|---|---|
50 Avenue S.W. | Geotechnical study | March (approx. 1 week) | Contractor completing bore holes to complete geotechnical study required prior to road construction. Flaggers on site to direct traffic during work. |
Glenmore Trail S.W.: Lake View Golf Course Section | Noise barrier replacement | Spring 2025 – Winter 2025 | Construction of the noise barrier at this location is currently in the procurement phase. A timeline will be established once a contractor is on board. The project team will notify residents in the area in advance of the construction start date. |
Crowchild Trail S.W. - East side (53 Ave. S.W. to 50 Ave. S.W.) | Noise barrier replacement | Spring 2025 – Winter 2025 | Construction of the noise barrier at this location is currently in the procurement phase. A timeline will be established once a contractor is on board. The project team will notify residents in the area in advance of the construction start date. |
Glenmore Trail S.W. repaving (Crowchild Trail to 14 St) | Milling and paving | Summer 2025 | Construction will be completed during off-peak daytime and nighttime work. The project team will notify residents in the area in advance of the construction start date. |
The City is working closely with the community to keep residents and business owners informed about upcoming work in the area.
You can find information on our upcoming events and view recordings of previous virtual events below.
Come learn about the planned work in the area and meet the project teams who will be delivering the improvements and new infrastructure at our collaborative information session.
Date: Wednesday, March 26, 2025
Time: 6:30 p.m. - 8:30 p.m.
Location: North Glenmore Park Community Association
This information has no legal status and cannot be used as an official interpretation of the various bylaws, codes and regulations currently in effect. The City of Calgary accepts no responsibility to persons relying solely on this information. Web pages are updated periodically.