Various Street Improvements Program
The City of Calgary’s Various Street Improvements (VSI) Program runs each year from April through to November and includes locations across the city.
The program manages the construction of miscellaneous improvements to existing roadway and mobility infrastructure, including turn bay extensions and/or widenings, intersection improvements, traffic calming features, sidewalks, pathways, transit facilities, and drainage solutions.
The priority of most of these projects is to improve safety, service levels, quality and accessibility. These projects are often related to development, transportation optimization capacity, Area Redevelopment Plans (ARP), safety, and other community issues.
Projects may take a few days to a few months to complete. Locations are marked on the Roadway activities map. Please note, locations may be added, removed or delayed due to budget availability and coordination with other City projects and initiatives. Additional project information will be added to this page once available.
Northeast street improvement projects
Location | Project description |
---|---|
11 Street N.E. | Transit pads |
1402 Centre Street N.E. | Curb and gutter lane |
19 Street N.E. from 41 Avenue N.E. to McKnight Boulevard N.E. | Pathway |
16 Avenue N.E. & 52 Street N.E. | Intersection Improvements |
24 Avenue N.E. & 1 Street N.E. | Curb extension |
32 Avenue N.E. at Nose Creek | Pathway |
36 Street N.E. at Rundle Station | Rebuild bus pad |
39 Avenue N.E. from Barlow Trail N.E. to 32 Street N.E. | Pathway |
46 Avenue N.E. at Nose Creek | Pathway |
47 Street N.E. & 50 Avenue N.E. | Left turn lane |
80 Avenue N.E. and Driveway 180m West of Saddlebrook Drive N.E. | Crosswalk improvements |
96 Avenue N.E. and East Leg Aurora Park Drive N.E. | Pathway |
Airport Tr N.E. & 68 Street N.E. | Intersection improvements |
Country Hills Boulevard N.E. Parks Access | Parking lot |
Country Hills Boulevard N.E. and Coventry Boulevard N.E. | Pathway |
Country Village Road N.E. from Harvest Hills Boulevard N.E. to Coventry Hills Way N.E. | Pathway |
Coventry Boulevard N.E. & Coventry Drive N.E. | Curb extension |
Maryvale Drive N.E. & Marlborough School N.E. (mid-block crossing Marlborough School) | Curb extension |
McKnight Boulevard N.E. from 4 Street N.E. to Trelle Boulevard N.E. | Pathway |
Saddletowne Bus Terminal | Driveway redesign |
Saddletowne Circle N.E. (80 Avenue N.E. to Taravista Drive N.E. | Pathway |
Townsend Street N.E. | Road reconstruction |
Northwest street improvement projects
Location | Project description |
---|---|
1 Avenue N.W. & 7 Street N.W. (Sunnyside School) | Curb extension |
1 Avenue N.W. & 8 Street N.W. (Sunnyside School) | Curb extension |
10 Street N.W. (72 Avenue to Hunterhaven Road N.W.) | Pathway |
1112 Arbour Lake Road N.W. | Curb extension |
14 Street N.W. & Cromwell Avenue N.W. | Curb extension and median refuge |
2 Avenue N.W. (16a Street N.W. to 18 Street N.W.) | Pathway |
20 Avenue N.W. & 4 Street N.W. | Intersection improvements |
44 Avenue N.W. & 4 Street N.W. | Curb extension |
48 Avenue N.W. (West of John Laurie Boulevard N.W. to North Haven Drive N.W. | Adaptative pathway conversion to permanent infrastructure |
5 Avenue N.W. & 23 Street N.W. | Curb extension |
5 Avenue N.W. & 27 Street N.W. | Curb extension |
631 17 Avenue N.W. | Back Lane Repair |
64 Avenue N. & Centre Street N. | Smart rights |
Collingwood Drive N.W. & Constable Road N.W. | Pathway |
Confederation Park | Storm drain |
Country Hills Boulevard N.W. & 12 Mile Coulee Road N.W. | Boulevard regrading |
Country Hills Boulevard N.W. & Nose Hill Drive N.W. | Turn bay extension |
Crowchild Trail N.W. between 24 St N.W. and Charleswood Drive N.W. | Sink hole |
Hansen Ranch N.W. | Sign installation |
Hidden Creek Boulevard N.W. & Hidden Creek Way N.W. | Permanent roundabout |
Hidden Valley Drive N.W. & Hidden Park N.W. | Curb extension |
Memorial Drive N.W. & 14 Street N.W. | Valve site access road |
McKnight Boulevard N.W. & 4 Street N.W. | Turn bay extension |
Panamount Boulevard N.W. & Panamount Street N.W. | Curb extension |
Panorama Hills Drive N.W. and Panamount Street N.W. | Curb extension |
Sarcee Trail N.W. & 112 Avenue N.W. | Intersection Improvements |
Scenic Hill Close N.W. | Berm upgrades |
Shaganappi Trail N.W. & 40 Avenue N.W. | Smart right |
Silver Springs Off Leash Area | Pathway |
Spyhill Landfill (11808 – 69 Street N.W.) | Curb repair |
Symons Valley Parkway N.W. & Evanston View N.W. | Crosswalk improvements |
Tuscany Drive N.W. & Tuscany Glen Road N.W. | Curb extension |
Southeast street improvement projects
Location | Project description |
---|---|
129 Avenue S.E. & Bonaventure Drive S.E. | Curb extension |
16 Avenue S.E. (60m West of Robson Crescent S.E.) | Curb extension |
17 Avenue S.E. (68 Street S.E. to 70 Street S.E.) | Pathway |
210 Avenue S.E. (East of Macleod Trail S.E.) | Pathway |
26 Avenue S.E. & 39 Street S.E. | Curb extension |
42 Avenue S.E. & 1 Street S.E. | Pathway and sidewalk reconstruction |
5 Avenue S.E. (West of Pensville Close S.E.) | Crosswalk improvements |
52 Street S.E. (50 Avenue S.E. to bus stop on S.W. corner) | Pathway |
52 Street S.E. at Rona | Intersection improvements |
5000 11 Street S.E. | Sidewalk at Calgary Food Bank |
61 Avenue S.E. & 44 Street S.E. | Intersection improvements |
64 Avenue S.E. & 11 Street S.E. | Intersection improvements and smart right |
84 Street S.E. & Rochon Avenue S.E. | Road replacement |
Acadia Drive S.E. & Ancourt Road S.E. | Curb extension |
Canyon Meadows Drive S.E. (Park Estates Drive S.E. to Parkland Boulevard S.E.) | Pathway |
Canyon Meadows Drive S.E. & Queensland Drive S.E. | Intersection improvements |
Cranston Drive S.E. & Cramond Drive S.E. | Curb extension |
Dartmouth Road S.E. & 24 Avenue S.E. | Sidewalk and curb extension |
Dover Community | Street improvements |
George Moss Park (74 Avenue S.E. west of 24 Street S.E.) | Sidewalk and curb extension |
Heritage Meadows Way S.E. | Left turn lanes |
Lake Bonavista Drive S.E. & Bonaventure Drive S.E. (North intersection) | Curb extension |
Lake Ontario (Sidewalk west of Lake Ontario Drive S.E) | Pathway |
McIvor Boulevard from 52 Street S.E. to New Brighton Way S.E. | Pathway |
Memorial Drive S.E. & 36 Street S.E. (SW & SE corners) | Smart right turns |
Rivercrest Drive S.E. & Riverglen Drive S.E. | Curb extension |
Seton Crescent S.E. & Seton Way S.E. | Intersection improvements |
Shawville Boulevard S.E. & 162 Avenue S.E. | Intersection improvements |
Shepard Landfill | Curb repair |
Sunvalley Boulevard S.E. & Sunharbour Road S.E. | Intersection improvements |
Southwest street improvement projects
Location | Project description |
---|---|
10 Avenue S.W. & 77 Street S.W. | Pathway and intersection improvements |
11 Avenue S.W. & 14 Street S.W. | Curb extensions |
130 Avenue S.W. & Wood Valley Gate S.W. | Curb extension |
14 Avenue S.W. - Centre Street S to 14 Street S.W. | Paving |
14 Avenue S.W. Strathcona Boulevard S.W. & 69 Street S.W. | Pathway |
17 Avenue S.W. near 77 Street S.W. | Pathway |
17 Avenue S.W. & 73 Street S.W. | Adaptative pathway conversion to permanent infrastructure |
21 Avenue S.W. (17A Street S.W. to 18A Street S.W.) | Adaptative pathway conversion to permanent infrastructure |
25 Avenue S.W. & 4 Street S.W. | Intersection improvements |
26 Avenue S.W. & 51 Street S.W. | Intersection improvements |
26 Avenue S.W. (77 Street S.W. to Elysian Cr S.W.) | Adaptative pathway conversion to permanent infrastructure |
326 Discovery Ridge Boulevard S.W. | Curb extension |
37 Street S.W. | Pathway |
37 Street S.W. & 66 Avenue S.W. (Lakeview curb ramps) | Curb extension |
38 Avenue S.W. & 20 Street S.W. | Curb extension |
4 Street S.W. (50 Avenue S.W. to 56 Avenue S.W.) | Adaptative pathway conversion to permanent infrastructure |
45 Street S.W. & 5 Avenue S.W. | Curb extension |
50 Avenue S.W. (20 Street S.W. & 14A Street S.W.) | Adaptative pathway conversion to permanent infrastructure |
535 St Moritz Drive S.W. | Pathway |
6 Avenue S.W. & 10 Street S.W. | Intersection improvements |
73 Grafton Drive S.W. (Glamorgan School) | Curb extension |
8 Street S.W. (Royal Avenue S.W. to 17 Avenue S.W.) | Curb extension and intersection rebuild |
85 Street S.W. (Broadcast Avenue S.W. to 8A Avenue S.W.) | Left turn lanes |
90 Avenue S.W. & 16 Street S.W. | Pathway connection |
90 Avenue S.W. & 24 Street S.W. | Intersection improvements and smart right |
90 Avenue S.W. & Bay Ridge Drive S.W. | Intersection improvements |
90 Avenue S.W. & Oakside Gate S.W. | Pathway connector |
Braeside Drive S.W. & Braniff Road S.W. | Curb extension |
Bridlecrest Drive S.W. & 24 Street S.W. | Curb extension |
Canyon Meadows Drive S.W. & 6 Street S.W. | Intersection improvements |
Canyon Meadows Drive S.W. & Canterbury Drive S.W. | Intersection improvements |
Centre Street S. & 13 Avenue S. | Curb extension |
Crowchild Trail S.W. 200m south of Bow Trail S.W. | Barrier repair |
Elbow Drive S.W. & 80 Avenue S.W. | Intersection improvements |
Heritage Meadows Way S.E. | Left turn lanes |
James McKevitt Road S.W. & Evergreen Street S.W. | Intersection improvements |
Longridge Drive S.W. | Pathway |
Macleod Trail & 194 Avenue S. | Concrete rehabilitation |
Old Banff Coach Road S.W. & Coulee Way S.W. (73 Street S.W.) | Crosswalk improvements |
Palliser Drive S.W. & 26 Street S.W. | Curb extension |
Shawnessy Drive S.W. (South of Shawmeadows Gate S.W.) | Curb extension |
Sifton Boulevard | Median replacement |
Strathcona Drive S.W. (West of Strathridge Grove S.W.) | Curb extension |
Wentworth Drive S.W. & Wentworth Road S.W.) | Curb extension |