14 Street S.W. Reconstruction - Anderson Road to Canyon Meadows Drive S.W.

Project update - September 2024

Project progress | 85% complete

14 Street re-opened; ongoing construction resumes

14 Street S.W. was reopened on August 19, though there will still be ongoing construction. Short, localized lane closures may be required when construction activities are occurring adjacent to travel lanes. Construction signage will be posted on-site to help direct traffic.

Construction is on track for substantial completion by the end of October 2024. The following construction activities are scheduled for the remainder of the project:

  1. Top lift paving for 14 Street S.W.
  2. Pathway along 14 Street S.W. and Anderson Road (adjacent to Dr. E.P. Scarlett High School)
  3. Landscaping
  4. Installation of post and cable fence
  5. Rehabilitation of the construction laydown area in the southwest corner of the Anderson Road and 14 Street S.W. intersection
  6. Installation of safety barrier

14 Street S.W. - Night paving taking place September 14 – 15, 2024

The contractor is required to complete final top lift asphalt paving at the south end limit of the project. All night work is scheduled on Saturday, September 14, 2024 to be completed by Sunday morning, September 15, 2024. Please note construction activities are dependent on several factors and paving timelines could change due to inclement weather and/or other unexpected circumstances.

Nearby residents may experience construction noise resulting from the night paving. We know this can be disruptive and we apologize for any inconvenience. Thank you for your patience and understanding.

Project overview

As part of a continuing program of major road restoration, The City is planning to complete road reconstruction on 14 Street S.W. from Anderson Road to Canyon Meadows Drive S.W.

There will be no changes to the number of lanes on the roadway as part of the current reconstruction project. A design will be completed for a potential future upgrade of this section of 14 Street S.W. from a two-lane road to a four-lane parkway, which may be warranted in the long-term.

By including the future four-lane road in the current design, The City is minimizing or eliminating potential throw-away costs.

A new pathway will be constructed along the east side of 14 Street S.W. and will be connected to the east to an existing pedestrian overpass on Anderson Road. Building this new pathway follows Council’s guiding principles and aligns with providing accessibility, mobility choices and connections for pedestrians and cyclists.

These upgrades will bring the design of the road up to modern standards, enhance safety and improve traffic flow, while improving connections for pedestrians and cyclists. 

Click to enlarge image

new pathway added map
Click to enlarge image

Project details

The project will include:

  • Pavement reconstruction and realignment of existing traffic lanes
  • Relocation of intersection/access into the Canyon Meadows Golf Course
  • Installation of a new stormwater system
  • Utility relocations
  • Streetlighting and landscaping
  • Addition of a new walking and wheeling connection along the east side of 14 Street S.W. from Canyon Meadows Dr. to Anderson Rd. with a connection along the south side of Anderson Rd. to the existing overpass at Dr. E.P. Scarlett High School.

A noise study has also been completed; based on the findings of this study, sound walls will not be installed as part of the current reconstruction project.

Project background

14 Street S.W. is a popular, high-use corridor which extends from north to south Calgary, connecting to important routes and destinations throughout the city. On the south end, the segment from Anderson Road to Canyon Meadows Drive S.W. is a two-lane rural road in need of rehabilitation.

The proposed reconstruction project would enhance safety and provide a more comfortable experience for all modes of travel, while helping to ensure the roadway remains in good condition for years to come.

Timeline

  • Finalize design: Early summer 2023
  • Construction start: Fall 2023
  • Construction completion: Fall 2024

Construction activities are dependent on several factors. Timelines could change due to inclement weather, underground conditions and/or other unexpected circumstances.


Stay connected

Sign up for email updates to receive news and notices about the project.

Connect with the project team

For more information, please contact the project team at 14StreetSW@calgary.ca


Budget

  • 14 St. S.W. Reconstruction $9 million
  • Canyon Meadows Dr. Resurfacing $1.5 million

Related links

​​​​​​

This information has no legal status and cannot be used as an official interpretation of the various bylaws, codes and regulations currently in effect. The City of Calgary accepts no responsibility to persons relying solely on this information. Web pages are updated periodically. ​

undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null