Development approvals timelines
Development permits ensure new developments align with the rules and regulations set out in both the Land Use Bylaw (LUB) and the Alberta Building Code.
Some development permits require a multidisciplinary review by planning and engineering specialists. Such applications may include:
- Commercial/Industrial/Mixed Use (Addition/New)
- Residential (Multi-residential development, townhouses, rowhouses) (New)
- Renovations to above, as well as changes to site plan (i.e., landscaping, parking, access), and exterior renovations
Development approvals | Target (calendar days) | Per cent of decisions within target (April 2023 - March 2024) | Average days (April 2023 - March 2024) |
---|---|---|---|
Single, semi-detached & duplex dwellings in the developed area |
90 | 76% | 72 |
Other technical development applications | 60 | 86% | 40 |
Subdivisions (by instrument) | 21 | 91% | 15 |
Multi-Disciplinary Development Permits |
120 | 82% | 90 |
Land use amendments |
180 | 85% | 147 |
Subdivisions (by tentative plan) |
60 | 86% | 39 |