Main Streets Bridgeland

Phase 2 – 1 Avenue N.E.

Project updates– April 2025

Bridgeland Main Streets project is moving into the third season of construction starting the week of April 14, 2025, with construction expected to be completed by fall 2025.  We will be starting construction with streetscape and infrastructure improvements along 1 Avenue N.E., progressing in stages along 1 Avenue N.E. from 8A Street to 4 Street N.E.

See the 2025 construction map.

See the parking access map.

The construction work hours are Monday to Saturday from 7 a.m. to 7 p.m., with occasional work on weekends, weekdays, and evenings/overnight as required.

During construction, here's what you can expect:

  • Temporary traffic detours, barriers, ramps, and accesses will ensure pedestrians and cyclists can travel safely through the area and still access their destinations.
  • Continued access to Bridgeland businesses - we will work directly with businesses to minimize the impacts of construction to their property as much as possible.
  • Temporary closure of some parking, roads, and potential road detours. Traffic will be maintained during construction, by way of local detours.
  • Temporary relocation of transit stops, Canada Post mailboxes, and/or Calgary Parking Authority pay machines.
  • An increase in on-site construction activity, including construction crews, vehicles and heavy equipment, and an increase in noise and vibration throughout construction.

2025 Street cleaning

As part of The City of Calgary’s Street Cleaning Program, The City’s street cleaning team will begin spring sweeps in the area starting the week of April 14, 2025. Temporary parking bans will be implemented on all side streets adjacent to 1 Avenue N.E. to facilitate this work, please be sure to watch for all parking signage. For more information, please visit Calgary.ca/sweep or contact 311.

  • April 15, 2025: The street cleaning team will sweep all avenues within Bridgeland over a one-day period.
  • April 17, 2025: The street cleaning team will sweep all streets within Bridgeland over a one-day period.

ENMAX Construction

As part of the Bridgeland Main Street Project, ENMAX Power is continuing utility upgrades along 1 Avenue N.E. Each stage is expected to last 4-6 weeks, depending on weather conditions. Work is underway in the following locations:

  • Started Feb. 24, 2025: Along 1 Ave. N.E. between 4 to 6 St. N.E.
  • Started March. 24, 2025: Along 1 Ave. N.E. between Edmonton Tr. and 6 St. N.E.

This work, which includes burying overhead powerlines and installing upgraded equipment, will be completed in stages over the next several months. For updates or inquiries, visit the project website or contact ENMAX’s Customer Relations Team at 403-514- 3990. You can also reach The City project team at bridgelandmainstreet@calgary.ca

Stop Control Changes – Spring 2025

We will be installing new traffic controls at several intersections along 2 Avenue N.E. Stop controls will be changed from East-West stopping, to North-South stopping, with the exception of the 6A, 8A and 10 Street N.E. intersections.

The goal of these changes is to improve safety for all roadway users, reduce vehicle speeding, and create a more viable cycling route along 2 Avenue N.E. We will continue to monitor the safety and performance of the new traffic controls and new curb extensions (bump-outs) along 2 Avenue N.E., to identify any potential opportunities for further roadway safety improvements for all users. 

A Wrap on the 2024 Construction Season

In 2024, we completed the streetscape improvements and infrastructure upgrades: on the north side of 1 Avenue N.E. between 6 Street to 7A Street N.E. and from 8A Street to 11 Street N.E.; also, improvements were made on the south side of 1 Avenue N.E. between 7A Street to 9A Street N.E. Additionally, five intersections along 2 Avenue N.E. were upgraded in 2024 as part of the Bridgeland Main Street project. This included widening sidewalks and upgrading street lighting to improve pedestrian safety, providing street furniture to enhance pedestrian comfort, beautifying the area with the addition of new naturalized turfs, decorative grasses, and new trees.

Check out some photos of the work we completed this year:

  • Contact us

    Do you have a specific question about the Bridgeland Main Street Construction project?

  • Stay connected

    Sign up for our email updates to receive ongoing updates about the Bridgeland Street Main Street construction project.

Timeline

upcoming-item

Category Icon and Label

Live 2025

Start Date | End Date

  • Ongoing investment in development 
  • Operations and maintenance

current-item

Category Icon and Label

Build 2022 – 2025

Start Date | End Date

  • Phase 1 (Edmonton Trail) 2022-2023
  • Phase 2 (1 Ave. N.E.) 2023-2025
  • Construction of designs based on streetscape master plan

past-item

Category Icon and Label

Design 2018 – 2021

Start Date | End Date

  • Pedestrian safety measures implemented
  • Detailed design work complete
  • Community engagement
  • Bridgeland Streetscape Master Plan completed and approved

past-item

Category Icon and Label

Plan 2017

Start Date | End Date

  • Land use redesignation and infrastructure assessment

past-item

Category Icon and Label

Strategize 2014 – 2016

Start Date | End Date

  • Public engagement and market studies

Project scope

The 1 Avenue N.E. Main Street underwent the “design” step of the Main Streets program in 2018 and 2019. Based on community feedback, technical analysis, and financial considerations, we created a plan to support the needs identified by the community.

Phase Two of the Bridgeland Main Street project involves operational and streetscape improvements along 1 Avenue N.E. from 4 Street to 11 Street, and along 2 Avenue N.E. between 6 Street N.E. to 10 Street N.E.

Work includes:

Please see the Roll Plot for more detailed information:

  • 4 Street N.E. to 6A Street N.E.
  • 6A Street N.E. to 8A Street N.E.
  • 8A Street to 11 Street N.E.

Widened sidewalks

More plants and trees

New street lighting along the road and sidewalks

New crosswalks with wheelchair ramps complete with tactile plates to help those with vision loss at intersections

Additional/upgraded pedestrian crossing signals at several intersections

Changes to intersection controls on 2 Avenue N.E.

New waste and recycling bins, bike racks and benches

Bridgeland Main Street – Phase 2 – 1 and 2 Avenues N.E.

The 1 Avenue Main Street vision encompasses numerous considerations, including:
  • A focus on urban design and placemaking.
  • Enhanced pedestrian safety and comfort.
  • Improved mobility options, including transit and cycling.
  • A design that is uniquely “Bridgeland-Riverside” and reflects its heritage and community identity.
  • Improved connections to park spaces and amenities.
  • Enhancing the community’s Main Street as a destination that will support existing and new local businesses.

A rendering of what 1 Avenue may look like can be found here.

Background

The City developed a Streetscape Master Plan for Bridgeland based on citizen feedback, technical analysis, and financial considerations.

The vision for the Bridgeland Main Streets project is to build a streetscape that includes well-designed, quality public realm elements and public space, that prioritize the pedestrian experience and will support ongoing redevelopment and a thriving economic environment. Once complete, it will offer a variety of safe, accessible mobility connections, new community gathering spaces, and a uniquely Bridgeland character.

The key features of Bridgeland Main Streets are:

  • Prioritize pedestrian safety
  • Enhanced landscaping for pedestrian comfort
  • Unique streetscape elements
  • New opportunities for community gathering
  • Improved mobility options

Frequently asked questions (FAQs)

Project information

What’s the goal of this project? What is The City trying to accomplish?

The Bridgeland Main Streets (BMS) project is improving sidewalks, intersections, and other public areas so the community is safe, accessible, and connected as it continues to evolve. Once complete, Calgarians will be able to shop, visit, and explore the community with ease and convenience.

How will this project address my property value?

Once complete, BMS will provide safe and accessible mobility connections, and new community gathering spaces. These improvements are expected to boost the local economy by attracting new businesses and investments.

To find out more information on how your property value is assessed please visit:  Property Assessment (calgary.ca). 

Why are some streets in Bridgeland not included in the project?

Due to budget and resource limitations, the Main Streets project is focusing on five intersections for new curb extension installations. After these improvements are complete, we will explore options to stop controls in the area to improve comfort and flow along 2 Avenue N.E. for pedestrians and cyclists.

Why are some roadways being narrowed?

One of our key project objectives is to reduce vehicle speeds and improve pedestrian safety along the 1 Avenue N.E. corridor. By widening sidewalks and adding curb extensions, we aim to reduce conflicts between drivers, cyclists, and pedestrians while also ensuring the accommodating of larger vehicles and buses. These curb extensions improve visibility for both pedestrians and vehicles while lowering vehicle speeds.

Why is this project focusing on non-vehicle changes when traffic is congested?

Main Streets projects encourage Calgarians to explore their communities through a variety of safe, accessible walking and wheeling connections. During engagement with the community, we heard and noted the vision and principles (below). 

  • Adding more trees and vegetation
  • Improving the sidewalks and lighting
  • Incorporating character features unique to this community
  • Improved pedestrian crossings
  • More options for seating and benches

These ideas, along with our project goals, guided our decision choices. Our project team has used engineering expertise along with data to review Bridgeland-Riverside’s transportation network.

Construction information

Will there be road closures and detours during construction?

Yes, there will be temporary closures of some streets and sidewalks. These localized closures are necessary to keep contractors, and the area, safe while they work. For detailed information about closures, detours, and other construction impacts, please refer to the Project Updates section of this page.

How will the design impact traffic flow, volume, and congestion?

  • On select blocks of 1 Avenue N.E. where active construction is happening, drivers will be detoured around to adjacent local roads (2 and Centre Avenues N.E.). We will close one direction of traffic in these areas and redirect vehicle traffic around the closure.
  • Pedestrians will have safe access along 1 Avenue N.E. with barriers, temporary ramps, and wayfinding signage to notify the community. We will ensure Calgarians can continue to access their favourite local businesses and organizations using temporary walkways or ramps.
  • We know that construction and detours can be impactful to a community. We will work with our colleagues, partners, and contractor to balance these impacts with completing construction safely and efficiently. This way, the community can still be enjoyed during construction, and enjoyed even more with new improvements once Bridgeland Main Streets is complete. 

When will construction be finished?

We aim to finish construction by the end of 2025, depending on the weather and other site constraints that may arise. This means the major, more road and sidewalk work will be largely done. We’ll be working on weather-dependent items like planting trees and finalizing street furniture in 2026. These final refinements will be less impactful in terms of detours and closures. You can find our anticipated construction timeline and updates in the Project Updates section of this webpage.

We look forward to celebrating the completion of the project with the community!

Why are there times when no crews are actively working within a construction zone?

  • Construction happens in stages and is often involves multiple specialized contractors or trades. As with all types of construction, certain work must be completed before other types of work can begin.
  • While every effort is made to align contractors and maintain work continuity within construction zones, factors such as weather, underground conditions or crew, material and equipment availability can impact workflow and scheduling.
  • To keep the work area safe and protected for pedestrians and drivers, safety barriers and detours may be left in place when crews are not active on site (for instance, outside of work hours or between work phases). Keeping barriers up also helps to expedite construction when crews arrive, by reducing the time required to set up the work zone.

What can I expect for business access and parking during construction?

Our team is committed to ensuring Calgarians can easily access and support Bridgeland-Riverside businesses. To complete construction quickly and efficiently and return service to the public as soon as possible, some driveways and accesses may be fully closed for a few weeks to rebuild new driveways. We will work with businesses and impacted properties to review opportunities to maintain access during construction for critical operational needs for pick-ups, deliveries, and more.

On-street parking will be available where possible, but temporary restrictions may be necessary to support construction activities. We are working closely with the Bridgeland-Riverside BIA to make sure everyone knows the community is still open for business.

How will landscaping maintenance (watering, weeding, etc.) be handled after construction?

The new landscaping will be managed by our contractor for three years following installation, as it is under warranty during this period. After construction is complete, maintenance responsibilities will transfer to the City of Calgary’s mobility teams.

Related links


This information has no legal status and cannot be used as an official interpretation of the various bylaws, codes and regulations currently in effect. The City of Calgary accepts no responsibility to persons relying solely on this information. Web pages are updated periodically. ​

undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null