About this project

Project update: April 2025

Construction upgrading pedestrian infrastructure along 14 Avenue S will begin the week of April 14 and is expected to be completed by the end of June.

Pedestrian infrastructure upgrades on 14 Avenue S will include:

  • Curb extensions
  • Installation of new wheelchair ramps
  • Concrete repairs to sidewalks

Construction details:

To limit the impact on businesses, commuters, and pedestrians, work will be conducted in short sections, starting at 14 Street and moving eastward toward Macleod Trail.

Temporary Impacts:

  • Traffic: The road will remain open, but there may be minor delays or changes in traffic patterns due to construction activities.
  • Sidewalks: Sidewalks will be open for pedestrians, although there may be occasional interruptions. Flag-persons will be present to assist with pedestrian activity, and detours will be in place as needed.
  • On-Street Cycling: On-street cycling will be facilitated throughout construction. However, there may be sections of the road guided by detour signs.
  • Driveway Access: We will do our best to keep driveway access uninterrupted. If driveway access will be temporarily affected, crews will provide the affected residents/businesses with at least 24 hours' advance notice.
  • Street Parking: Street parking will be temporarily removed in active work zones to ensure the safety of motorists and construction crews. Access to street parking will be restored as work is completed in each section.

Thank you for your cooperation and patience as we work to improve infrastructure in the area. Your safety remains our top priority.

Changes to Parking and Loading Zones

Click to enlarge the image. Please refer to the attached graphic for a detailed illustration of these changes.

Project schedule – 2024 to 2026

Construction began in the fall of 2024 and is expected be completed by the summer of 2026.

We are currently finalizing the next stages of the construction schedule for both 14 Avenue S and 15 Avenue S and will provide more information in the coming weeks. 

Traffic Signal and Lighting Upgrades (in progress):

  • New traffic signals on 15 Avenue at Macleod Trail and 2 Street SW will support the new wheeling lanes.
  • Lighting levels on 14 and 15 Avenue S are being rebalanced to reduce dark spots, enhancing safety for everyone in the area.

Concrete repairs on 14 Avenue (in progress)

  • Concrete repairs to sidewalks on 14 Avenue S will take place from the fall of 2024 until the spring of 2025.

Pedestrian Infrastructure Upgrades (Mid-April 2025 to June 2025):

  • Curb extensions and wheelchair ramps will improve pedestrian accessibility along both corridors.

Protected Two-Way Wheeling Lane (schedule TBD):

  • The existing painted wheeling lane on 15 Avenue S is being upgraded to a protected two-way lane from 11 Street S.W. to Macleod Trail.
  • The existing painted wheeling lane on 14 Avenue S is being removed.

Repaving (schedule TBD):

  • Both 14 Avenue S and 15 Avenue S will be repaved.

Traffic Flow Changes (schedule TBD):

  • The 14 Avenue S corridor will be converted back to a two-way road. Parking on both sides will remain, and the existing painted wheeling lane will be removed.

Water Main Replacement (schedule TBD):

  • The water main on 15 Avenue S from 6 Street S.W. to 8 Street S.W. will be replaced. Residents and businesses directly impacted will receive additional information in the coming weeks, including timing and what to expect. 
  • Should it be necessary to disrupt water service, residents and businesses will be provided a temporary water supply. All affected customers will receive notice at least a day in advance.

Project scope clarification

Initially, we planned a protected two-way wheeling lane on the north side of 15 Avenue between 12 Street S.W. and southbound Macleod Trail.

After further review, we have shifted the project one block east, extending from 11 Street S.W. to northbound Macleod Trail. This adjustment ensures better connectivity with the future entertainment district and the LRT.

As funding has now been secured for the next phase of this project, we will be
completing the following work:

  • Upgrading the existing painted wheeling lane to provide a protected two-way
    wheeling lane on the north side of 15 Avenue S between 11 Street S.W. and
    northbound Macleod Trail. This will require the removal of parking on the
    north side of the road. (See rendering image below)
  • Changing the 14 Avenue S corridor back to a two-way road. Parking will be
    maintained on both sides of 14 Avenue S, and the existing painted
    wheeling lane will be removed.
  • Repaving both corridors as part of this project between 14 Street S.W. and Macleod Trail.
  • Upgrading existing streetlights and wheelchair ramps along both corridors.
  • Replacing the water main on 15 Avenue S from 6 Street S.W. to 8 Street S.W.
    Additionally, we’ll be implementing cathodic protection to preserve the pipes
    beneath the corridor. Cathodic protection helps prevent corrosion and
    extends the lifespan of underground infrastructure.
15 ave
Rendering of the proposed protected two-way wheeling lane on 15 Avenue S

Community engagement

On Tuesday, September 10, 2024, we hosted a virtual community information session from 6 p.m. to 7 p.m.

This session provided an opportunity for the public to learn about the upcoming Mobility Improvements project on 14 and 15 Avenue S. Participants received updates on the project scope, timelines and had the chance to ask questions.

We appreciate everyone who attended and hope you found the information valuable.

Missed the virtual session or want to revisit?

We also have a comprehensive FAQ document available, addressing questions we didn't have time to cover during the session.

Please see the image for the project scope and location.

Project Design

Plan view of 14 Avenue S. and 15 Avenue S., between 12 Street S.W. and Macleod
Trail S.E.

Project background

As part of the 17 Avenue S.W. Construction Project, detours were required along 14 Avenue and 15 Avenue. Both corridors were temporarily converted to one-way roads, allowing westbound travel on 14 Avenue and eastbound travel on 15 Avenue between 1 Street S.E. and 12 Street S.W.

Despite maintaining parking on both sides of the road, the corridors' width encouraged speeding. Consequently, interested parties urged the City to enhance the experience for pedestrians and cyclists. In response, one-way wheeling lanes (for bicycles, scooters, etc.) were installed in the direction of traffic to provide consistent wheeling facilities and narrow the vehicular travel lanes.

We collected data, reviewed operations, and gathered feedback from Calgarians in 2020 and 2021 to develop a design recommendation for permanent infrastructure along the 14 and 15 Avenue S corridors. We are now moving forward with constructing the permanent infrastructure.

Project alignment with Council priorities

This project supports Calgary's council priorities by:

  • Enhancing safety and accessibility: Dedicated wheeling lanes for bike, scooter and skateboard users improve safety by providing protected spaces.
  • Promoting social equity: Protected wheeling lanes offer cost-effective, healthy, and inclusive transportation options, enhancing citywide accessibility goals and equitable access to transportation.
  • Addressing climate goals: Encouraging wheeling and walking reduces greenhouse gas emissions, contributing to Calgary’s climate resilience efforts.
  • Strategic infrastructure investments: This initiative is part of a broader strategy to invest in Calgary's infrastructure, improving safety, reducing congestion, and fostering a healthier community.

Project funding

The project has $12.4 million in funding secured for design and construction. This project is being jointly funded by the Government of Canada using the Active Transportation Fund and The City of Calgary under Calgary’s Pathway and Bikeway Network (5A) program and the Downtown Strategy program. These programs fund active infrastructure to make our neighborhoods safer, more inclusive, and accessible for everyone.

Frequently asked questions

Parking

collapsed all

Safety and Accessibility

Loading zones

Winter Maintenance and Usage

collapsed all

Wheeling lane usage

collapsed all

Traffic counts

Engagement and communication

collapsed all

Project timeline

  • Engagement:
    • Phase 1: Identification (September 2020)
    • Phase 2: Prioritization (January 2021)
  • Concept design: Complete
  • Detailed design, enabling works: Complete
  • Construction starts: Late Spring 2025 *We are here* 

Engagement

We incorporated the feedback received, along with technical recommendations, to develop the design for this project.

Stay connected

Sign up for our email updates to receive the most up-to-date information about this project.

Budget

$12.4 million

Questions?

Related links


This information has no legal status and cannot be used as an official interpretation of the various bylaws, codes and regulations currently in effect. The City of Calgary accepts no responsibility to persons relying solely on this information. Web pages are updated periodically. ​

undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null