Piling and road realignment at Barlow Trail and 114 Ave S.E.
Piling for the bridge at 78 Avenue S.E.
Just south of Douglas Glen station, the Green Line will be elevated as it crosses 114 Avenue and Barlow Trail S.E. This package of work is to prepare the area for construction of the elevated guideway.
Contract status
A Request for Proposals was posted on April 4, 2025. The submission deadline is April 28, 2025. When the contract is awarded, this page will be updated with the supplier.
Scope of work
The scope of work includes drilling concrete piles, utility relocation and road realignment (grade/base/pave).

Anticipated Start Date: May 2025
Anticipated Completion Date: November 2025